These are the significant events in the construction of the
Double Luck Garage during July, 2001.
2 July, 2001
Click on the image to see it full size (145K).
A cement pad has been placed at the entrance to the Garage, so that we can back out
and turn easily.
It will also be a nice place to wash cars and trucks!
Click on the image to see it full size (135K).
The tractor door can finally be used per design.
A cement ramp has been poured to allow the tractor to be driven into its reserved parking space.
All it needs a little gravel at the bottom of the ramp to ease the transition, and for someone (I am not
mentioning any names) to move that lumber out of the way!
13 July, 2001
With the conversion of the construction financing into a regular mortgage, the construction process is
officially complete.
There is, of course, a "punch list" of items for the builder to complete or repair.