| 2 December, 2000 |
|

Click on the image to see it full size (86K).
Insulation is being installed by 31W Insulation (Katy, TX) in the attic and into all of the walls, as can be
seen in this view of the bath room.
We can also see that the shower stall has been moved from the porch and placed into its permanent location.
We are scheduled to begin installing car siding onto the interior walls on Monday, 4 December.
|
| 6 December, 2000 |

Click on the image to see it full size (72K).
Compare this to the previous photo.
The bath room now has sheet rock installed by Zeisert Drywall (Houston, TX), and green board is installed in
the shower areas.
In the main room, sheet rock has been hung on the ceiling.
The walls will soon be covered with "car siding", wooden planks that used to be placed on the
interior walls of railroad cars.
|
| 9 December, 2000 |
|

Click on the image to see it full size (93K).
Remember that missing gable over the ticket window?
The rework for the roof is complete and all of the
Hardiplank siding has now been installed.
|
| 17 December, 2000 |
|

Click on the image to see it full size (69K).
The interior walls of the Station are covered in car siding by Ceasar Gatica's Trim
(Houston, TX).
This material was formerly used in the construction of railroad cars, so it seems particularly appropriate for
this building.

Click on the image to see it full size (127K).
The sewer lines from the Station have been run to the new septic system installed by
Braden Septic Services (Hempstead, TX) and are ready to be connected.
|