These are the significant events in the construction of the
Double Luck Station during July 2001.
2 July, 2001
Click on the image to see it full size (167K).
A small shed roof has been placed on the side wall to cover the compressor and gas tank for the beer machine.
The new brewing equipment is on order and will be arriving any day.
Hopefully, we will make the move to the big house before it does, because I will be sorely tempted to start
brewing immediately!
13 July, 2001
With the conversion of the construction financing into a regular mortgage, the construction process is
officially complete.
There is, of course, a "punch list" of items for the builder to complete or repair.